Liquid-Cooled GPU Colocation in Australia: A Buyer's Guide
A practical checklist for customer-owned GPU racks: power, coolant, residual air, network, commissioning and the evidence to request before contracting.
· Arvica Cloud · Enterprise buyer's guide
Begin with the exact system
A GPU count does not define a facility interface. Obtain the manufacturer's bill of materials and site-preparation pack for each server or integrated rack. Record the platform, maximum and typical system input, rack dimensions and weight, service clearance, coolant envelope, remaining air heat, delivery method and support owner. NVIDIA's DGX GB rack documentation describes compute trays, switch trays, power shelves, a busbar and liquid manifolds as one system; that OEM example does not establish what a proposed Arvica site can host. [1]
Separate IT load from facility power
Ask for the exact electrical feed, protection, redundancy, metering and maintenance-isolation design. Include network, storage and management devices in the scope. A planning estimate such as facility power ≈ IT load × assumed PUE can compare scenarios, but does not establish grid approval, rack allocation or measured operating PUE. Require a signed design basis, one-line diagram and witnessed commissioning plan before treating capacity as deliverable.
Agree on the liquid-cooling boundary
A coolant distribution unit can separate the technology cooling system from the facility water system. The Open Compute Project describes that boundary and the CDU's control role. The OEM must approve coolant chemistry, temperature, flow, pressure, filtration and leak-response limits; the facility designer must explain how they will be monitored and maintained. Name the owner of manifolds, CDUs, pumps, valves, sensors, alarms and isolation. A generic 'warm-water ready' label is not enough. [2]
Plan for residual air and failure modes
Liquid cooling does not remove every air-cooling requirement. NVIDIA's DGX GB rack guide says CPUs and GPUs use cold plates while networking, storage and other parts remain air cooled. Validate room airflow, humidity and condensation limits alongside liquid supply. Test what happens when a pump, cooling path, power feed or network link fails, and agree who responds. [1]
Include network, storage and operations
Document east-west compute traffic, north-south customer and storage traffic, out-of-band management, cross-connects, routing, tenant isolation and data location. NVIDIA's GB300 NVL72 architecture separates these paths, but the fabric, ports and speed in a customer proposal must be confirmed for the actual equipment. Ask who owns firmware, remote hands, spares, telemetry and incident response. [3]
Ask for a commissioning evidence pack
Before contracting, request the site's actual approval status, OEM revision, power and cooling test plan, network and storage design, responsibility matrix, service milestones, contract terms and remedies for delay. Mark each item confirmed, proposed or unknown. An expression of interest begins engineering and commercial review; it is not an allocation.
Arvica's planned Queensland option
Arvica is planning a high-density, liquid-cooled AI data centre in Swanbank, Queensland, targeting approximately 2.2 MW of IT capacity, subject to grid connection, engineering design, regulatory approvals and customer demand. Expressions of interest are open for enterprise GPU colocation and dedicated AI infrastructure. The facility is planned, not operational; the target does not represent approved grid capacity or allocated racks. Use the existing non-binding colocation EOI for your system requirements.
Frequently asked questions
Does liquid cooling remove the need for room air cooling?
No. Confirm the remaining air-cooled components and their heat rejection for the exact OEM system. [1]
Can an EOI reserve a GB300 rack?
No. An EOI starts technical and commercial review. Hardware fit, site readiness and any allocation need later written confirmation.
Is the 2.2 MW figure an approved power allocation?
No. It is Arvica's approximate IT planning target, subject to grid connection, engineering design, regulatory approvals and customer demand.
Download an editable worksheet to agree scope, compare configurations and decide whether to stop, adjust or scale. An evaluation method, not a customer case study.
Compare scope, allocation, storage, networking and pilot acceptance before committing to a B300 node. Includes a worked cost formula, not a supplier price.
Build a representative inference test with model, precision, context, concurrency and quality targets. Connect the measured result to a transparent GPU budget.